Welcome to Emergency Multi-Sector Rohingya Crisis Response Project (EMCRP)
Emergency Multi-Sector Rohingya Crisis Response Project (EMCRP) will help Bangladesh to cope with the world’s fastest growing exodus, where the Rohingya population outnumbered the local community more than three folds in the Teknaf and Ukhia Upazilas in Cox's Bazaar District.
The project will help build and rehabilitate basic infrastructure, improve community resilience and help prevent gender-based violence against the forcibly displaced Rohingya population.
The project will build and improve - multipurpose cyclone shelters cum schools, relief administration & distribution center, multipurpose community service centers, hat bazaars, firefighting warehouses, roads, footpaths, drains, culverts, bridges, lightning arresters and install solar street lights inside the camps with the help of Local Government Engineering Department (LGED).
The World Bank approved a $165 million grant to help Bangladesh to provide basic services and build disaster and social resilience for the Rohingya who have fled violence in Myanmar and sought shelter in the Teknaf and Ukhia Upazila of Cox’s Bazar district.
EMCRP/W01 - Improvement of 6 nos Hat Bazar
Start Date:
Physical Progress: 30
Financial Progress: 30
End Date:
EMCRP/W02 - Construction of warehouse for firefighting equipment .
Start Date:
Physical Progress: 37
Financial Progress: 37
End Date:
EMCRP/W03 - Relief Administration and Distribution Center
Start Date: 2020-05-18
Physical Progress: 100
Financial Progress: 97
End Date: 2021-06-01
EMCRP/W04 - Construction of 30 Multipurpose Community and Service Center
Start Date:
Physical Progress: 40
Financial Progress: 40
End Date:
EMCRP/W05 - Construction of internal road, footpath, drainage and side slope protection
Start Date:
Physical Progress: 15
Financial Progress: 12
End Date: 0000-00-00
EMCRP/W06 (dropped) - Rehabiliation of blocked hilly chorra with excavation of canal in Ukhiya Upazilla
Start Date:
Physical Progress: 0
Financial Progress: 0
End Date:
EMCRP/W07 - Field Office (EE Cox's Bazar) Extension with renovation
Start Date: 2019-12-10
Physical Progress: 100
Financial Progress: 97
End Date: 2021-10-12
EMCRP/W08 - Construction of 6 RCC Girder bridges at different roads under Cox's Bazar District.
Start Date: 2021-03-10
Physical Progress: 100
Financial Progress: 95
End Date: 2022-09-17
EMCRP/W09 - Construction of 4 RCC Girder bridges at different roads under Cox's Bazar District.
Start Date: 2021-03-10
Physical Progress: 96
Financial Progress: 83
End Date: 2022-09-17
EMCRP/W10 - Construction of 12 nos. New School cum disaster shelter buildings
Start Date: 2020-03-25
Physical Progress: 77
Financial Progress: 59
End Date: 2021-08-22
EMCRP/W11 - Construction of 11 nos. new School cum disaster shelter buildings in Ukhya (9 nos.) and Teknaf (2nos
Start Date: 2020-12-13
Physical Progress: 43
Financial Progress: 25
End Date: 2022-05-03
EMCRP/W12 - Rehabiltiation of 12 camp connecting roads around/within camp
Start Date: 2020-12-13
Physical Progress: 0
Financial Progress: 0
End Date:
EMCRP/W13 - Improvement of 8 Access Road to different camps with culverts
Start Date: 2020-01-29
Physical Progress: 99
Financial Progress: 71
End Date: 2021-08-05
EMCRP/W14 - Improvement of 7 Access Road to different camps with culverts
Start Date: 0000-00-00
Physical Progress: 100
Financial Progress: 97
End Date: 2020-01-14
EMCRP/W15 - Construction of 4 RCC roads
Start Date: 2020-12-13
Physical Progress: 93
Financial Progress: 87
End Date:
EMCRP/W16 - Construction of 4 RCC roads under Cox's Bazar District
Start Date: 2020-12-13
Physical Progress: 86
Financial Progress: 80
End Date:
EMCRP/W17 - Improvement of 8 roads and construction of culverts with side drains
Start Date: 2020-12-13
Physical Progress: 76
Financial Progress: 70
End Date:
EMCRP/W18 - Improvement of 8 roads roads and construction of culverts with side drains
Start Date: 2020-12-13
Physical Progress: 84
Financial Progress: 78
End Date:
EMCRP/W19 - Improvementof 10 roads roads and construction of culverts with side drains
Start Date: 2020-12-13
Physical Progress: 96
Financial Progress: 91
End Date: 2020-11-30
EMCRP/W20 - Improvement of 11 roads roads and construction of culverts with side drains
Start Date: 2020-12-13
Physical Progress: 100
Financial Progress: 99
End Date: 2020-12-13
EMCRP/W21 - Improvement of 17 roads roads and construction of culverts with side drains
Start Date: 2020-12-13
Physical Progress: 86
Financial Progress: 82
End Date:
EMCRP/W22 - Improvement 15 Roads with culverts and side drains in Ukhya and Teknaf (1-6; 5.75km)
Start Date: 2020-12-13
Physical Progress: 58
Financial Progress: 48
End Date:
EMCRP/W23 - Improvement 18 Roads with culverts and side drain
Start Date: 2020-12-13
Physical Progress: 74
Financial Progress: 54
End Date:
EMCRP/W24 - Improvement of 7 roads with culverts and side drains
Start Date: 2020-12-13
Physical Progress: 53
Financial Progress: 51
End Date:
EMCRP/W25 - Strengthening and widening of 10 roads under Cox's Bazar Districts
Start Date: 2021-04-15
Physical Progress: 87
Financial Progress: 79
End Date: 2022-10-21
EMCRP/G01 - Purchase of 34 Nos motor cycles
Start Date: 2020-03-22
Physical Progress: 100
Financial Progress: 100
End Date: 2020-06-30
EMCRP/G02 - 1500 Street Lamps
Start Date: 2021-08-19
Physical Progress: 100
Financial Progress: 93
End Date: 2021-03-21
EMCRP/G03A - 90 Nos Early Streamer Emission Lightning Protection System
Start Date: 2019-07-30
Physical Progress: 100
Financial Progress: 100
End Date: 2020-11-30
EMCRP/G03B - 285 Early Streamer Emission Lightening Protection System
Start Date:
Physical Progress: 100
Financial Progress: 78
End Date:
EMCRP/G04 - 5 Nos 10000+1000 Liter water Tanker
Start Date: 2019-04-11
Physical Progress: 100
Financial Progress: 100
End Date: 2020-11-30
EMCRP/G05 - 6 Nos Fire and Rescue Vehicle
Start Date: 2019-10-10
Physical Progress: 100
Financial Progress: 100
End Date: 2020-11-30
EMCRP/G06 - 19 Nos Towing Vehicle (Pick-up type with CAF and water)
Start Date: 2019-11-30
Physical Progress: 100
Financial Progress: 100
End Date: 2020-11-30
EMCRP/G07 - 15 Nos firefighting portable pump (small)
Start Date: 2019-06-25
Physical Progress: 100
Financial Progress: 100
End Date: 2020-03-01
EMCRP/G08 - 2 Nos fire service Command Vehicle
Start Date: 2019-09-12
Physical Progress: 100
Financial Progress: 100
End Date: 2020-11-30
EMCRP/G09 - 2 Nos fire service Command Vehicle
Start Date: 2021-01-14
Physical Progress: 100
Financial Progress: 100
End Date: 2021-01-14
EMCRP/G10 - 5 Nos Ambulance
Start Date: 2019-09-12
Physical Progress: 100
Financial Progress: 100
End Date: 2020-03-01
EMCRP/G11 - 6 Nos Rescue Boat
Start Date:
Physical Progress: 0
Financial Progress: 0
End Date:
EMCRP/G12 - 1 Nos Fire Fighting Turn Table/Arial Platform Ladder
Start Date: 2020-02-02
Physical Progress: 100
Financial Progress: 100
End Date: 2020-11-30
EMCRP/G15A - LS Office Furniture
Start Date:
Physical Progress: 0
Financial Progress:
End Date:
EMCRP/G15B - LS Office Furniture
Start Date:
Physical Progress: 0
Financial Progress:
End Date:
EMCRP/G16A - 1No Minibus
Start Date: 2019-06-12
Physical Progress: 100
Financial Progress: 100
End Date: 2020-03-23
EMCRP/G16B - 1No Minibus
Start Date: 2019-06-12
Physical Progress: 100
Financial Progress: 100
End Date: 2020-03-23
EMCRP/G17 - 1 Mobile Maintenance Vehicle
Start Date:
Physical Progress: 0
Financial Progress:
End Date:
EMCRP/G18 - 1 No Generator
Start Date: 2019-07-01
Physical Progress: 100
Financial Progress: 100
End Date: 2019-12-30
EMCRP/G19 - LS Stationary
Start Date:
Physical Progress: 0
Financial Progress:
End Date:
EMCRP/G20 - LS Survey and Soil Test items
Start Date:
Physical Progress: 0
Financial Progress:
End Date:
EMCRP/G21 - LS Social and Environmental Survey items
Start Date:
Physical Progress: 0
Financial Progress:
End Date:
EMCRP/W26 - Strengthening and widening of 11 roads under Cox's Bazar Districts
Start Date: 2021-09-07
Physical Progress: 71
Financial Progress: 64
End Date: 2022-06-30
EMCRP/AFW02 - Improvement of Boro Jamchari Rubber Dam in Ramu & Sadar
Start Date:
Physical Progress: 85
Financial Progress: 60
End Date:
EMCRP/AFW11 - Construction of 17 nos. new School cum Disaster shelter buildings with access roads in Cox's Bazar D
Start Date: 2022-05-22
Physical Progress: 56
Financial Progress: 36
End Date:
EMCRP/AFW12 - Construction of 10 nos. new School cum Resilience shelter buildings incldung 9.20 KM access roads an
Start Date:
Physical Progress: 11
Financial Progress: 10
End Date:
EMCRP/AFW14 - Construction of 7 RCC roads under Cox'sBazar District including culvert and drain
Start Date:
Physical Progress: 20
Financial Progress: 11
End Date:
EMCRP/AFW04 - Improvement of Gorokghata Jetty in Moheskhali and Darbarghat Jetty in Kutubdia
Start Date:
Physical Progress: 3
Financial Progress: 4
End Date:
EMCRP/AFW07 - Improvement of Existing Fire Service at Ukhiya and Teknaf
Start Date:
Physical Progress: 10
Financial Progress:
End Date:
EMCRP/AFW08 - Building Construction for Fire Service Civil Defense (FSCD) at Cox's Bazar
Start Date: 2022-08-22
Physical Progress: 14
Financial Progress: 3
End Date:
EMCRP/AFW09 - LGED Building Improvement at Cox's Bazar
Start Date:
Physical Progress: 30
Financial Progress:
End Date:
EMCRP/AFW15 - Improvement of road by RCC pavement in Mirakata from Ch. 00-2000m in Kutubdia
Start Date:
Physical Progress: 95
Financial Progress: 93
End Date:
EMCRP/AFW16 - Improvement of 4 roads roads under Cox's Bazar District
Start Date:
Physical Progress: 5
Financial Progress:
End Date:
EMCRP/AFW17 - Improvement of 5 roads roads under Cox's Bazar District
Start Date:
Physical Progress: 50
Financial Progress: 26
End Date:
EMCRP/AFW18 - Strengthening and widening of Gorakghata - Shaplapur Janata Bazar Road, ID-422492001
Start Date:
Physical Progress: 98
Financial Progress: 93
End Date:
EMCRP/AFG01 - Water Vehicle, Toying Vehicle and Portable Pump
Start Date:
Physical Progress: 100
Financial Progress: 100
End Date:
EMCRP/AFG02 - Delivery hose, Hand control branch pipe and Foam making branch pipe
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG03 - Smoke ejector, Power chain saw and Power cutter
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG04 - Breathing apparatus, Diving aparatus, Heat protective suit and Fireman suit
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG05 - Gas detector, Stretcher and Extension ladder,
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG07 - Spreader
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG08 - Ram Jack
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG09 - Life detecting device
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG10 - Helmet
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG13 - Computer Accessories
Start Date:
Physical Progress: 100
Financial Progress:
End Date:
EMCRP/AFG17 - Solar Light
Start Date:
Physical Progress: 28
Financial Progress:
End Date:
EMCRP/AFG18 - Supply and Installation of Solar PV Nano Grid
Start Date:
Physical Progress: 55
Financial Progress:
End Date:
EMCRP/AFG19 - Supply and Installation of Solar PV Nano Grid
Start Date:
Physical Progress: 19
Financial Progress:
End Date:
EMCRP/G22 - Soap, Hand Sanitizer and Disinfected Spray
Start Date: 2020-06-20
Physical Progress: 100
Financial Progress: 100
End Date: 2020-11-17
EMCRP/AFW11-A - Construction of new School cum Disaster shelter buildings
Start Date: 2022-05-11
Physical Progress: 40
Financial Progress: 26
End Date:
EMCRP/W04-A - Construction of Multipurpose Community and Service Center
Start Date:
Physical Progress: 16
Financial Progress: 12
End Date:
330
Active Project
4792
Submission Reports
16184
Reports Images
91
Users
Quality & skill
Consultant
We are using top quality materials to build project.
No compromise with quality products.
LGED Engineers
We are using top quality materials to build project.
No compromise with quality products.